Gas tanks

Lag time fast systems

Surface O3 concentrations


TO DO


Saturday, May 25th

Daily checks

  • Lab temperature = 21.8°C, AC temperature = 68F.
  • Case temperature: fast O3 = ~22.9°C, fast NOx = ~19.0°C.
  • Fast O3 clock synchronized with time.nist.gov on 5/25/2019 at 8:34am (AST).
  • Drierite OK (change it tomorrow).
  • Fast O3: OK, NO flow rate OK.
  • Fast NOx: OK.
  • Gas tanks: OK.

Puff system

3 injections at (fast NOx time):
2019-05-25 08:53:45
2019-05-25 08:55:24
2019-05-25 08:56:36


Friday, May 24th

Today we carried a bunch of equipment to the flux hut: Anssi’s intrument, our enclosure systems + associated equipment (pumps etc.), and two calibration tanks for the PTR/TOF/MS. The ice was too thin so we carried everything on the boardwalk…it took us all day…!


Thursday, May 23rd

Daily checks

  • Lab temperature = 20.7°C, AC temperature = 68F.
  • Case temperature: fast O3 = ~22.2°C, fast NOx = ~18.8°C.
  • Drierite OK.
  • Fast O3: OK, NO flow rate OK.
  • Fast NOx: OK.

Puff system

5 injections at (fast O3 time):
2019-05-23 08:03:33
2019-05-23 08:11:20
2019-05-23 08:12:30
2019-05-23 08:13:59
2019-05-23 08:15:22

GC/MS

On VI inlet system “Indicators”:
* Advance GC start (s) = 10 instead of 360.
* GC run time (s) = 1200 instead of 1500.

NPL run (600 s): TL_20190521_13

NPL run is good. New sequence started: GCMS_Toolik_20190523.sequence.
Inlet system:
0) Std2 BVOC
2) Ambient BVOC
3) Stop
Time between samples = 4200 s.

We will most likely have to make changes in the SIM method because of the new retention times.


Wednesday, May 22nd

Daily checks

  • Lab temperature = 21.7°C, AC temperature = 68F.
  • Case temperature: fast O3 = ~22.7°C, fast NOx = ~18.6°C.
  • Drierite OK.
  • Fast O3: OK, NO flow rate OK.
  • Fast NOx: OK.
  • GC/MS: running, water level OK.
  • Gas tanks: OK.

Fast NOx/O3 systems

  • Reorganize sample line
    The sample line first goes to the fast NOx, then to the fast O3. However, while the fast NOx is pumping 1 L/min, we send 1.2 L/min of Zero Air during calibrations. 0.2 L/min doesn’t make it to the instrument and goes back in the sample line, to the fast O3. During a calibration, a fraction of NO can thus be transported through the sample line to the fast O3 (and this NO will react with O3). Jacques suggested that we switch the order of the “tees” connected to the sample line so that the fast O3 is connected first.

Done 9:40-9:53am AST.

  • Puff system

I performed several injections between 10:40-11:00am AST. Unfortunately, the status of the fast NOx lag time valve is not saved in the VI (Jacques saved the fast O3 lag time valve instead). He will update the VI and I’ll do more puff tests when it’s done.

GC/MS

The chromatograms look weird, at least very different from what we got last year.

Today’s chromatogram:

Last year:

I compared the acquisition methods (in :D/MassHunter/GCMS/1/data/Toolik_GCMS_data/acqmeth.text). While Front SSZ Inlet He used to be at 200°C, Detlev changed it to 100°C on 12/09/2018. According to Jacques, this shouldn’t make any difference.

I connected the NPL tank to STD3 inlet.
Inlet system sequence:
0) STD3 BVOC (2400 s)
1) Stop
This is chromatogram TL_20190521_12.

NPL run last summmer (TL_20180728_08):

The separation of the peaks is not as good. Jacques remembers that there is now “Advanced GC start = 360 s” on the inlet system VI (Detlev asked for this), meaning that the GC actually starts 6 min earlier - the oven temperature is thus higher (because it’s been running for 6 more minutes) when the injection is done. This influences the retention times and potentially the separation.

Miscellaneous

  • We synchronized the fast O3 and the PTR-TOF-MS clocks.
    Control Panel > Date and Time > Internet Time > Check Automatically synchronize with an internet time server: time.nist.gov. Synchronization done at 3:04 pm AST. The fast O3 is now ~1min30s ahead of fast NOx.
  • Anssi built the tent! The one we bought is too small (6 x 6 x 6) for our two autosamplers and Anssi’s instrument. He bought the same model but 8 x 8 x 8 instead - we’re using his tent.

Tuesday, May 21st

Fast O3 calibration

Based on the calibration performed on Sunday, we know that the fast O3 is biased low by ~28-30%. Conversion from counts to ppb has to be updated.

O3 span = 0.000445 becomes 0.000612
offset = 0.11 becomes -1.47

Changes made to VI at 6:46pm AST.
Data from the slow and fast O3 are now ~comparable (keeping in mind that slow O3 was 3% too low compared to calibrator).

WS/WD sensor

Our sensor is off by ~80 degrees compared to data from the station (data available here.). I adjusted the position of the sensor accordingly at ~4pm local time.

Drierite

Drierite changed on both fast NOx and O3 (at ~1:50-2pm local time). Put drierite in oven at 210°C for 1 hr (LAB 2).

GC/MS

The settings in the sequence of the inlet system were wrong; use settings from last summer (BVOC settings are different from OVOC settings):
* sample time = 2400
* sample flow = 1.25
* backflush time = 180
* desorb time = 300
* flash heat time = 2
* inject time = 30
* bakeout temp = 325 * bakeout time = 40
* carrier flow = 1.25
Started new sequence on GC/MS (and inlet system): GCMS_Toolik_20100521.sequence.xml

Fast NOx

Note that the fast NOx data are now being saved in the fast O3 data files.
Columns headers:
* date fast O3 * time fast O3 (hhmm)
* time fast O3 (ss.s)
* counts
* O3 concentration (ppb)
* 0 fast O3 - NO valve status or lag time valve
* 1 fast O3 - NO valve status or lag time valve
* date fast NOx
* time fast NOx (hhmm)
* time fast NOx (ss.s)
* counts
* 0 or 1 (1 = auto mode)
* 0 or 1 (if NO or NOx)
* 0 or 1 (1 if calibration)
* 0 to 7: step in calibration

I performed a few tests with Jacques.
* O2 generator not stable. Changed the fittings at the outlet (see pic below), was damaged. O2 flow is now stable. Jacques still wonders whether the O2 might be contaminated (we see spikes from time to time) - Order ultra high purity O2.

  • The signal was still unstable and the background occasionally pretty high. We performed several tests in order to identify a potential leak. Couldn’t find anything. We ended up disconnecting/reconnecting the PMT high voltage and signal cables (at the top rear of the instrument - see pic below).

Monday, May 20th

WS/WD sensor

I need to replace the Reed Switch.
1. Disconnect WS/WD rear of MET Controls box
2. Disconnect anemometer from tower
According to instructions:
3. Open the sensor housing
4. Disconnect the wires
TOP to BOTTOM: RED, BLACK, YELLOW, GREEN, WHITE.
5. Push switch cartridge out of its seat. Clean off any old sealant from the top plate assembly.
Done
The WS constantly increases. Something’s wrong. Jacques suggests that the sensor counts the # of rotations but doesn’t seem to convert to m/s. Something’s wrong in the VI. Problem fixed! Jacques made changes in the VI.
New VI: METTower_Toolik_190520.vi

Daily checks

  • Lab temperature = 21°C, AC temperature = 68F.
  • Case temperature: fast O3 = ~22°C, fast NOx = ~17.6°C.
  • Drierite OK.
  • Fast O3: OK, NO flow rate OK.
  • Fast NOx: OK.
  • GC/MS: running, water level OK.
  • Gas tanks: OK.

Inventory

  • I talked to Justin (Toolik manager) about the canopy tent. We agreed that we can build it without asking BLM (quote: “better ask for forgiveness than permission”). He will let us know if BLM comes visit - if so, we will pack everything. The plan is for Anssi and I to build it tomorrow. It’s going to rain Wed/Thur/Fri so we can make sure it’s waterproof before we install instruments in it.
  • O3 sonde prep unit + O3 sondes (x2) + NOAA laptop: LAB1.
  • Helium tanks for balloon (balloon grade): 3 large ones + 1 smaller one.
  • Kestrel in Box#2 (warm storage).
  • Kestrel works with 1 AA battery.
  • Cold storage (south entrance): CPS is currently using the building for construction work/storage. They’re leaving Toolik on June 6th. I’ll check with them if we can use the building before that to store the balloon.

Sunday, May 19th

O3 calibration

I let the calibrator stabilize for ~1hr.

  • Slow O3

Set to 0 ppbv from 10:20am (AST) to 10:30.
Set to 25 ppbv from 10:30 to 10:40.
Set to 50 ppbv from 10:40 to 10:50.
Set to 100 ppbv from 10:50 to 11:00.
Set to 200 ppbv from 11:00 to 11:10.

  • Fast O3

Started calibration at 2:14pm AST (delete data ~20-30 min before, took me several attempts to connect the sample lines). Ended calibration around 4pm AST.

Daily checks

  • Lab temperature = 22°C, AC temperature = 68F.
  • Case temperature: fast O3 = ~22°C, fast NOx = ~19°C.
  • Drierite OK.
  • Fast O3: OK, NO flow rate OK.
  • Fast NOx: OK.
  • GC/MS: running, water level OK.
  • Gas tanks: OK.

Saturday, May 18th

GC-MS

Jacques did a air/water check and a tune yesterday evening : everything looks ok.
Sequence restarted: BVOCs.
Method used: BVOC_SCAN_SIM_180731.
Datafile: TL_20190518_01 to _50.
Sequence on inlet system: 1) 0-air BVOC (changed to Std2 = Breathing Air on 5/20/19 at 4:35pm local time) 2) to 13) Ambient Air
14) Reset

Miscellaneous

  • Talked to the EMT after what happened yesterday and we now have a fire extinguisher in the flux hut (on the floor, right when you enter, below the heater).
  • Made room in the hut (took the MET rack apart). The MET controls box and the O3 instrument are now on top of the fast NOx/O3 systems. That’s the best option I could come up with.

  • We successfully crossed the lake with the PTR-TOF-MS. The instrument is now in the flux hut and Catie is working on it.

  • We pulled a sample line through the Arctic pipe for the PTR-TOF-MS. ST1 and ST2 lines are out of the pipe.

Question for Detlev: On the picture below, the filter on the left is ours (fast O3/NOx systems), the one on the right is for the PTR-TOF-MS. Do you think they are too close to each other or that their inlet might interfere with ours? I just want to make sure that this setup is okay.


Friday, May 17th

Make room in the hut for Lu/Catie’s instrument

Catastrophe! While slightly moving the NPL tank, a short-circuit happened. I saw sparks and the GC/MS stopped. Everything that was connected to CKT 10 stopped. Strange thing, the fast NOx instrument stopped as well (at least the UPS + fan of H20 pump + laptop). NO flow on fast O3 instrument dropped to 0. I think the line between the NPL tank and the GC/MS touched CKT 10 and that’s how everything happened (see pics below). Jacques and I disconnected everything (computer, GC/MS, UPS) from CKT 10 and connected to CKT 17 instead. GC/MS restarted, fast NOx as well. We will check tomorrow that everything is indeed okay.

The NO flow dropping to 0 on the fast O3 has actually nothing to do with the short-circuit. The needle valve was not sufficiently open. Problem fixed. Keep an eye on this NO flow to make sure it doesn’t drop to 0 again.

Pics of the NPL tank line, CKT 10 and floor below CKT 10.

Fast systems

  • pump box outside and protected from rain.
  • fast O3 and NOx restarted
  • The fast NOx PMT temperature was too high, that was because the H20 pump was not working properly (air bubbles). Problem fixed.
  • The O2 flow on the fast NOx is highly variable (from 170 to 200). Don’t know why. After lunch, varies from 190 to 200. Keep an eye on that in the next couple days.
  • Background on fast NOx seems pretty high - Double check that tomorrow.
  • Double-checked that fast NOx is sampling from outside (cf high background). Here is what I have:
  • Double-checked that zero air is connected to fast NOx system and zero air tank opened.
  • Save fast NOx data on fast O3 laptop: USB-serial cables (COM 15 on fast O3, COM 8 on fast NOx) connected by NULL modem cable. Jacques is updating the VIs to make the data transfer possible.

Flux hut upgrades


Thursday, May 16th

I made it to Toolik after a 10hr-drive. There’s still snow in Atigun Pass but snow is gone pretty much everywhere else.